Case study
Phased Overnight Repainting at a 24/7 Veterinary Site
A completed circulation area following phased overnight redecoration by Black & White Property Services.
Black & White Property Services delivered a substantial internal redecoration programme at Moorview, a continuously operating veterinary site. The work covered corridors, access routes and reception areas while maintaining the site's day-to-day operation.
- Delivered by
- Black & White Property Services
- Site
- Moorview veterinary site
- Sector
- veterinary and clinical environments
- Project type
- phased redecoration and building-fabric improvement
- Relevant services
- commercial decorating, surface repairs and out-of-hours works
The challenge
The building remained operational around the clock. Busy circulation areas had accumulated impact damage and general wear, including damaged plaster, holes, deteriorated finishes and worn door frames. The programme therefore needed to be phased and completed out of hours with careful coordination around staff, patients and access routes.
The approach
A two-person team was planned across an extended series of overnight shifts. The documented scope included:
- making good damaged plaster and filling surface defects;
- caulking and preparing walls and woodwork;
- improving worn door frames where practical;
- applying a three-coat eggshell finish;
- colour-matched glosswork where required;
- using access equipment for higher areas;
- completing corridors and reception in phases to minimise disruption.
The working programme allowed approximately 12–14 nights for corridors and access ways, followed by a further 5–7 nights for reception areas.
Operational delivery
The project required more than straightforward decorating. Each section had to be prepared, repaired and finished while preserving safe access through a live clinical environment. Overnight scheduling and phased handovers allowed the veterinary site to continue operating while the improvement programme progressed.
Result
The programme refreshed heavily used clinical circulation and reception spaces, repaired accumulated damage and provided a coordinated finish across multiple operational areas.
Both reception areas, rear hallways and additional areas were repainted as part of the phased programme.
Have a similar requirement?
Explore commercial decorating or contact Black & White Facilities with the property address, the problem and the result you need. Include photographs and access details where useful.